Client Eagle Mountain City
Location Eagle Mountain, UT

This signal is the 6th of 6 signals CRS has designed on Pony Express over a two year period. Our design signalized this 4-way stop controlled intersection, including adding turn lanes, left-turn phasing, modified Safe Routes to school striping, and upgrading ADA ramps to meet current standards. The project was funded by Eagle Mountain but utilized UDOT standards and the State furnished materials process. CRS exceeded project expectations by coordinating with the local elementary school for Safe Routes to School changes and creating a bid package for construction to accommodate the school calendar.

Client

Eagle Mountain City

Location

Eagle Mountain, UT

Sectors and Services

Put Our Experience to Work for You. View Our Project Portfolio